隐私权政策

The whole process control of the decoration project construction of the hotel guest room model room(1)

Hotel model room decoration project, from 0 to 100 full process summary

Hotel decoration is a huge system engineering, there are capital, quality, duration, and other aspects of concerns, whether it is the investor or the construction site, first do the model room is responsible for the smooth delivery of the entire project. Therefore, before doing large-scale construction will make a model out, as a reference for the future.

1, hotel decoration project why do model rooms?

The immediate answer is: it’s easy to spot problems. There are generally two main ways to find problems. First, the design aspects, such as furniture, lamps, soft installation are reasonable. Second, the construction aspect, such as whether the construction process is qualified, and then, is conducive to large-scale construction in the future to control the duration.

2, hotel model room is generally doing what content?

Mainly rooms, other such as restaurants, lobbies and so on because of its space does not allow, generally, very few Party A will ask or the construction party will choose to do. In addition, if the types of high-end hotel rooms, generally will also choose the number of rooms to do a model, can highlight its representative.

Next, share the key points of control for the five-star model room project 0-100. You can see the control points of projects 0-100, from line control, drawing deepening, to product construction, waterproof control, grass-roots control, surface control, etc. through the complete project case.

Engineering Overview: The project is funded by xx Group Co., Ltd., which covers an area of 37 acres and is 16 stories high. Located at the xx address, the five-star hotel, with approximately 780 rooms, has entered into a management agreement with xx Hotel Management Group.

01

The “early” phase of the project

1.1

Engineering overview

1.2

Management and team structure

1, management responsibilities

Project Manager: Implementation of company policy, project management, quality, progress, safety, and other overall control of the project.

Construction workers: construction planning, construction line, material quantity verification, declaration, to maintain the unity of the team construction process.

Quality officer: line, size review, quality inspection, data declaration, technical bottoming, covert acceptance, handover acceptance.

Materialist: The main material tender and a variety of auxiliary materials price comparison and procurement work, responsible for the procurement of materials.

Deepening design: program deepening, node diagram, check typography and line drawings and coordinate the unity of each of the same sets.

Safety officer: safe and civilized construction management; Temporary facilities, temporary electricity safety management;

Warehouse Manager: material storage acceptance, sending and receiving, registration, to provide a reasonable material plan;

2, management structure

3, team personnel structure

1.3

Construction objectives are established

1.4

quality control

1, quality objectives

2, quality control points (ceiling).

3, product packaging construction

4, line control points

Inter-model control line release line requirements

The inter-model control line release line requirements

Following the company’s requirements to produce paint plates, line personnel and carpentry band leader unified the distribution of The island tape measure, to ensure the unity and accuracy of measurement tools

1.5

Safe and civilized control

1, the goal of security civilization

  • Eliminate deaths and major injury accidents;
  • to eliminate the occurrence of occupational diseases;
  • to eliminate the occurrence of occupational diseases;
  • 100%safe bottom rate and 100%safety hazard rectification rate;
  • Electric and gas welding “two certificates, one guardianship” compliance rate of 100%.

2, management measures and systems

  • Safety technology bottoming system
  • Safety production inspection system
  • Fire safety management system
  • Fire safety inspection system
  • Construction of temporary electricity regular inspection system
  • Safety education and training system
  • Pre-shift security activities system

3, security key management projects

  • Temporary electricity
  • Welding job
  • Construction tools

4, key management measures

  • Temporary electrical tissue design
  • Construction power management program
  • Tool acceptance record
  • Temporary electricity protocol
  • Temporary electricity acceptance records

1.6

Duration plan

1, the schedule requirements

  • Prepare a schedule of project schedules
  • Collect information (photos, minutes of meetings, Party A, general package, supervision and design communications, etc.) available for constructionvisas;
  • Regularly report weekly and monthly schedules
  • Materials: Because the project is in the model room construction stage, the use of materials is small to actively guide suppliers to actively cooperate with the construction work to provide quality materials.
  • Personnel: according to the needs of the site and the owner’s requirements for appropriate deployment of personnel, to avoid manual waste.

02

The Project Start phase

2.1

Drawings deepen

1, the model inter-drawing drill-down list

Wood finished facades are largely optimized

Wood finished facades are largely optimized

Shower glass partition optimization

TV background wall optimization

Top-faced wood finishes are optimized for seam retention

Glass break and top-face outlet optimization

2.2

Waterproof construction requirements between models

1, waterproof key area analysis

2, on-site large-scale, small-scale production

2.3

Product-oriented decoration

1, productized ceiling

△Disclaimer:

Some of the above pictures and information are from the Internet, and the copyright belongs to the original author and his company; this article is for study and research purposes only and cannot be used for commercial purposes. If this article infringes your rights, please contact us to delete; some articles The original author could not be contacted due to various reasons during the push. If copyright issues are involved, the original author is kindly requested to contact us and deal with it immediately.

12345